Almergeb Cement Plant
Located on the coastal road in Almergeb area, west of Al-Khums and approximately 117 km east of Tripoli.
Total area
40 Hectares
Product Type
Ordinary Portland Cement
Production Lines
Two Lines
First Line
The implementing company
German company "Polysius"
Designed Capacity
100,000 ton/year
Production start
1968
The plant, however, was ultimately decommissioned due to low productivity, outdated equipment, and low economic viability.
Second Line
The implementing company
German company "Polysius"
Designed Capacity
300,000 ton/year
Implementation Start
1971
Production start
1974
As a result of technical problems in 1982, production was completely halted. Raw materials hall, electric refinery, sampling station, and radiological analyzer were all overhauled in 1993, allowing the line to restart. With the restart, imported bauxite was replaced with locally sourced clay, bringing all raw materials within reach of the plant.
Number of Workers
National
Worker
240
Foreign
Worker
3